Construction restart of Dos Hermanos bridge hits
another snag
By : JOSE L. CARMONA/CARIBBEAN
BUSINESS
Volume: 36 | No: 12
Page : 04
Issued : 03/27/2008
U.S. Army Corps of Engineers requests additional information and
clarification of certain aspects of mitigation plan submitted by
Highway & Transportation Authority
The restart of the $25 million construction work on Dos Hermanos
Bridge in Condado, which according to the Puerto Rico Highway &
Transportation Authority (HTA) was slated to begin this month and
was later postponed to April after three years of inactivity,
could face yet another delay as the U.S. Army Corps of Engineers (Usace)
has requested additional information and clarification of certain
aspects of the mitigation plan the local agency submitted to Usace
Feb. 27.
Demolition work on the bridge was halted in 2005 after Usace
denied the renewal of the construction permit because of changes
in its original design and the discovery of coral colonies by the
National Marine Fisheries.
Dos Hermanos bridge is the main thoroughfare between Condado—San
Juan’s main tourism sector—and the islet of Puerta de Tierra / Old
San Juan.
As previously reported (CB, Feb. 14), demolition work on the
existing bridge could not begin until HTA had submitted a complete
mitigation plan for seagrass transplantation and coral relocation,
as well as a baseline assessment of seagrass at the mitigation
site, and had obtained approval from Usace.
HTA must cut the existing bridge piers where coral colonies are
present and relocate them at the southeast end of Dos Hermanos
Bridge.
According to Usace, on Feb. 27, HTA submitted the compensatory
mitigation plan and baseline characterization assessment as
required by the two special conditions set forth by Usace permit
No. SAJ-1998-5848, which authorizes the replacement of the bridge
and the discharge of fill material in open waters for the
construction of abutment shafts for piers and rip-rap revetments.
Upon review of the mitigation plan submitted by HTA, Usace
determined in a letter dated March 14 that necessary information
was still required for a complete mitigation plan and requested
clarification of certain information included in the documents
submitted by HTA Feb. 27.
The March 14 Usace letter, of which CARIBBEAN BUSINESS obtained a
copy, mentions several discrepancies in the HTA mitigation plan,
including one involving differing information between baseline
assessment and the mitigation plan, discrepancies in the different
mitigation sites, a different plot design, insufficient details on
a modified “plug” technique for transplanting seagrass and
concerns over the monitoring period stated by HTA in the
mitigation plan.
“Item 9(a) on page 20 of the mitigation plan stated that
monitoring will be performed biannually for the five years of the
duration of the mitigation permit. The Corps [Usace] has concerns
with this sentence. In accordance with the special condition of
permit No. 7, the five years of the monitoring period will
commence on the date of the submittal of the initial report and
not during the duration of the mitigation permit.”
The March 14 Usace letter also requested additional information as
to the proposed transplanting schedule (in terms of proposed dates
of initiation and completion), status on the performance standards
(whether the mitigation is achieving the established goals and
objectives) and a written description of the proposed measures for
protecting the mitigation site during the five-year monitoring.
Usace gave HTA 15 working days from the date of the March 15
letter to respond. As of press time Monday afternoon, HTA had
notified Usace it was expecting to respond to the March 15 Usace
letter that same day (March 24). Calls to HTA Communications
Director Irma Mullero were not returned as of press time Monday.
“HTA’s response will be evaluated by the Usace project manager. In
the coming days, we will be informing HTA if the submitted
information is correct and it clarifies the concerns addressed in
our March 15 letter,” indicated Usace Public Affairs Officer Elsa
Jiménez.
In the March 14 letter, Usace cautions HTA that work performed
below the mean ordinary waterline or the discharge of dredged or
fill material without compliance with the terms and conditions of
the permit could be subject to enforcement action.
“In other words, HTA can do preparation work at the site, but
cannot start construction work below the waterline until Usace
approves the mitigation plan,” added Jiménez.
|